Bechtel Gladstone said that the final Train 1 module on the Santos GLNG site was installed last week.
All 82 modules have now been set in place, marking a major step in the completion of the Train 1 section of the plant. Bechtel crews are currently completing the piping and electrical works in preparation for first gas on site, the company said.
Bechtel is constructing a two-train LNG plant on Curtis Island for Santos GLNG. In total, 111 modules will be produced for Train 1 and Train 2.