Dong Energy has informed that the third deck of the Hejre platform’s topside has been lifted into place.
The topside for the Hejre platform is under construction in South Korea.
Dong Energy says there are lots of details and challenges in connection with the construction of the Hejre platform. The platform’s topside will consist of more than 13,000 tonnes of structural steel, 600km of cables, 40km of pipes, three lifts and more than 100 supplier packages (pumps, compressors, tanks, etc) arriving regularly from all over the world. The company says it is a large and complex task to put all these things together, and it is expected to take more than 1.8 million working hours to produce the platform’s topside.