Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›National Grid, Elia Welcome Cross-Border Cable Approval
Offshore Wind

December 2, 2014 · about 11 years ago

National Grid, Elia Welcome Cross-Border Cable Approval

National Grid Nemo Link Limited has welcomed Ofgem’s decision on regulatory regime for the proposed Nemo Link interconnector between UK and Belgium. The project is being jointly developed by UK National Grid and Elia, the Belgian transmission system operator and would be the first electricity link b

1 minutes read
  • LinkedIn
  • X
  • Email

National Grid Nemo Link Limited has welcomed Ofgem’s decision on regulatory regime for the proposed Nemo Link interconnector between UK and Belgium.

The project is being jointly developed by UK National Grid and Elia, the Belgian transmission system operator and would be the first electricity link between the two countries.

Alan Foster, European Business Development Director, National Grid said:

“The decision to allow the interconnector to be built under the new cap and floor regime gives us more certainty about the revenue streams and keeps the project on track to reach a final investment decision in Spring 2015. It’s encouraging news too for the other interconnector projects we are developing with other European partners“.

Stefaan Vanden Berghe, Elia’s Large Infrastructure Projects Director said:

“We are pleased that the regulatory regime for the Nemo Link interconnector between Belgium and UK is defined and is currently being published, both in Belgium and UK. This is an essential condition for Elia to assess and decide on the final investment decision in Spring 2015.”

The proposed 1000 megawatt interconnector would run for approximately 130 kilometres between Zeebrugge and Richborough in Kent. This would be the third electricity interconnector connection between Kent and Europe. The BritNed interconnector between Isle of Grain and the Netherlands went into operation in 2011 and the IFA interconnector between Sellindge and France began in 1986.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free