Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›Siemens Hands Over BorWin2 to TenneT
Offshore Wind

January 30, 2015 · about 11 years ago

Siemens Hands Over BorWin2 to TenneT

Siemens has handed over the first North Sea grid connection, BorWin2, to TenneT following successful completion of test runs. The offshore platform of the BorWin2 grid connection is located around 100 kilometers off the German coast – northwest of the island of Borkum, after which the project was na

2 minutes read
  • LinkedIn
  • X
  • Email

Siemens has handed over the first North Sea grid connection, BorWin2, to TenneT following successful completion of test runs.

The offshore platform of the BorWin2 grid connection is located around 100 kilometers off the German coast – northwest of the island of Borkum, after which the project was named.

“This is the first offshore grid connection worldwide to take up commercial operation with efficient direct-current technology,” stated Jan Mrosik, CEO of the Siemens Energy Management Division.

With this grid connection it is now possible to transmit 800 MW of clean electricity from wind power, enough to supply around one million German households.

Back in April 2014, Siemens installed the 16,000-ton platform at 39-meter-deep North Sea location.

The network operator TenneT contracted the consortium consisting of Siemens and the Italian cable specialist Prysmian for the BorWin2 offshore grid connection in summer 2010. Siemens is now implementing five North Sea grid connection projects for TenneT: HelWin1 (576 MW) and HelWin2 (690 MW) off of Helgoland, BorWin2 (800 MW) and BorWin3 (900 MW) off of Borkum and SylWin1 (864 MW) off of Sylt.

The next three grid connections, Sylwin1, HelWin1 and HelWin2, are nearly completed and are scheduled to take up commercial operation in the first half of 2015. Commissioning of this fifth grid connection, BorWin3, is scheduled for 2019. The grid connections implemented by Siemens for TenneT will have a total transmission capacity of more than 3.8 gigawatts (GW), providing electricity from offshore wind power to supply around five million households.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free