Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›Freeport LNG files Train 4 resource reports
Clean Fuel

June 15, 2015 · about 11 years ago

Freeport LNG files Train 4 resource reports

Freeport LNG filed draft resource reports 1 and 10 with the Federal Energy Regulatory Commission as part of the pre-filing process of the train 4 project at the Quintana Island facility.

2 minutes read
  • LinkedIn
  • X
  • Email

Freeport LNG filed draft resource reports 1 and 10 with the Federal Energy Regulatory Commission as part of the pre-filing process of the train 4 project at the Quintana Island facility.

The filed draft resource reports give a general project description and alternatives for the Train 4 project.

Resource report 1, along with resource reports 2 through 13, will collectively make up the environmental report to be submitted as part of the application of Freeport LNG to FERC for authorization to site, construct, and operate natural gas liquefaction facilities within Freeport LNG’s authorized facilities on Quintana Island near Freeport, stands in the filing.

The project will add a fourth propane pre-cooled mixed refrigerant liquefaction unit which will provide additional liquefaction capacity of approximately 5.1 million metric tons per annum of LNG for export, which equates to a natural gas throughput capacity of approximately 0.72 billion cubic feet per day.

A feed gas receiving and metering station will also be constructed. The project also involves construction of all required utility, auxiliary and control systems including, common utilities, spill containment systems, fire and safety systems, one electric substation, security systems and plant roads, Freeport LNG said.

Freeport LNG is requesting that the Commission issue authorization by September 2016 to site, construct, and operate the train 4 project and anticipates requesting authorization in October 2016 to commence construction in November 2016.

Construction and start-up of the project will be completed in approximately 39 months, with completion scheduled approximately 6 to 9 months after the completion of the first three trains authorized under the liquefaction project. Freeport LNG expects the project will be completed and ready to commence LNG exports in January 2020.

Freeport LNG expects the project will be completed and ready to commence LNG exports in January 2020.

[mappress mapid=”17317″]

LNG World News Staff; Image: Freeport LNG

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelNews

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free