Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›DEME Bags EUR 130 Million Deal for Belgian Modular Offshore Grid
Offshore Wind

August 17, 2017 · about 9 years ago

DEME Bags EUR 130 Million Deal for Belgian Modular Offshore Grid

Belgian transmission system operator Elia has awarded Dredging International, part of the DEME Group, with a contract for the subsea cable installation for the Modular Offshore Grid (MOG) in the Belgian part of the North Sea.

1 minutes read
  • LinkedIn
  • X
  • Email

Belgian transmission system operator Elia has awarded Dredging International, part of the DEME Group, with a contract for the subsea cable installation for the Modular Offshore Grid (MOG) in the Belgian part of the North Sea.

The installation scope includes the supply, installation and maintenance of the submarine power cables. The contract has been valued to approximately EUR 130 million.

DEME will deploy its new fleet of vessels to carry out the works, including hoppers Minerva and Scheldt River, and DP3 cable installation vessel Living Stone, entering the DEME fleet in 2017 and operated by Tideway.

The cables will be produced by Hellenic Cables, a Greek manufacturer, as a subcontractor for DEME.

Elia’s Modular Offshore Grid, or so-called electricity plug, includes an Offshore Switchyard Platform (OSY) located about 40 kilometres off the Zeebrugge coast, to which four wind farms will be connected. Submarine cables will link the platform with a substation in Belgium, where produced wind energy will be fed to the Belgian onshore grid.

One 220kV power cable will be installed along a 4,5 km route between the Offshore Switchyard Platform and the first wind farm’s platform. Also, two 220kV submarine power cables of approximately 39 km each will be installed from the Offshore Switchyard Platform to the onshore connection point located on the beach in Zeebrugge.

The Modular Offshore Grid is scheduled to be operational in the third quarter of 2019.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindBusiness & FinanceStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free