Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›Maersk Connector Loads First Nemo Link Cables
Offshore Wind

August 30, 2017 · about 9 years ago

Maersk Connector Loads First Nemo Link Cables

DeepOcean’s Maersk Connector has completed loading of the first phase on the Nemo Link cables in the port of Blyth.

1 minutes read
  • LinkedIn
  • X
  • Email

DeepOcean’s Maersk Connector has completed loading of the first phase on the Nemo Link cables in the port of Blyth.

Two 59-kilometre-long 400kv HVDC XPLE cables were simultaneously spooled from a freighter onto the 7,000 te. split capacity duel concentric carousel.

The vessel is now on her way to the UK coast near Ramsgate where she will commence the installation of the cables. The cables will be buried by DeepOcean’s T3200 trencher.

The second phase of the project is scheduled to be completed by DeepOcean in the second quarter of 2018.

Nemo Link will consist of two subsea and underground cables connected to a converter station and an electricity substation in Belgium and the UK, which will allow up to 1,000MW of electricity to flow in either direction between the two countries.

Under the contract with J-Power Systems, a division of Sumitomo Electric, DeepOcean is responsible for all marine works associated with the installation and protection of the HVDC bundled cables from the transition joint bay in Kent, UK to the transition joint bay in Zeebrugge, Belgium.

The offshore works is scheduled to be completed in 2018. In addition to the installation and trenching of the bundled cable system, DeepOcean’s work scope includes route surveys and engineering, pre-lay grapnel runs, out of service cable clearance, pre-sweeping in sandwave areas and crossings construction.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November