Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›EA1 Leads to One of Europe’s Largest Archaeological Digs in 2017
Wind Farms

October 12, 2017 · about 9 years ago

EA1 Leads to One of Europe’s Largest Archaeological Digs in 2017

The onshore works for East Anglia ONE underground cable have unearthed a historical treasure for the Suffolk area. So far evidence from the Bronze Age, Iron Age, Roman period, Anglo-Saxons and into the medieval period has been found, making this one of Europe’s largest archaeological digs this year,

2 minutes read
  • LinkedIn
  • X
  • Email

The onshore works for East Anglia ONE underground cable have unearthed a historical treasure for the Suffolk area. So far evidence from the Bronze Age, Iron Age, Roman period, Anglo-Saxons and into the medieval period has been found, making this one of Europe’s largest archaeological digs this year, according to ScottishPower Renewables.

The archaeological excavations have been funded by ScottishPower Renewables, prior to the construction of a 37km underground cable, which will connect the 102 turbines from the East Anglia ONE Offshore wind farm to a new electricity converter station at Bramford.

Wardell Armstrong was commissioned to oversee archaeological works across 60 hectares of Suffolk countryside, working closely with Suffolk County Council. Up to 400 archaeologists have been involved in the work since February, with a peak on-site workforce of around 250 at any given time, as well as 20 members of the Ipswich and District Metal Detector club.

Joanna Young , Stakeholder Manager at ScottishPower Renewables, said: “Hundreds of archaeologists and metal detectorists combing over fields in Suffolk is not the first thing you think of when you imagine an offshore windfarm – but it highlights the wide range of efforts needed to build a major energy project like ours.

“We decided early on to invest in underground cables to take power from the offshore windfarm to the National Grid, rather than building pylons. This means laying cables under the ground and roads and rivers and railways across a 37km stretch. We need to make sure that we do this work in a sensitive manner, and it is important to record all items of archaeological significance.”

The cable laying project for East Anglia ONE will begin in the next few months, ScottishPower Renewables said, and construction work is already underway at the onshore substation site in Bramford.

Offshore work begins in 2018, with the 102 Siemens 7MW turbines due to be installed in 2019, before the project is fully operational during 2020.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Saipem hands Saudi jack-up fleet to ADES in strategic shallow-water exit
  2. 2Valeura advances Gulf of Thailand expansion with PTTEP farm-in approval
  3. 3Santos broadens Asia-Pacific LNG portfolio with Canadian supply and 10-year POSCO deal
  4. 4Borr Drilling keeps three jack-up rigs as it reorganizes Mexico ops with stake sale

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free