Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›LNG›Golar expects first LNG from Cameroon FLNG in December
LNG

November 30, 2017 · about 8 years ago

Golar expects first LNG from Cameroon FLNG in December

LNG shipper Golar LNG said on Thursday that it expects production of first commercial liquefied natural gas from its FLNG Hilli Episeyo located offshore Kribi in Cameroon to take place around year end. The world’s first FLNG conversion arrived in Cameroon on November 20, and hook-up and connection t

1 minutes read
  • LinkedIn
  • X
  • Email

LNG shipper Golar LNG said on Thursday that it expects production of first commercial liquefied natural gas from its FLNG Hilli Episeyo located offshore Kribi in Cameroon to take place around year end.

The world’s first FLNG conversion arrived in Cameroon on November 20, and hook-up and connection to risers and umbilicals is now underway, according to Golar.

To remind, the FLNG departed Keppel Shipyard on October 1 and left Singapore for Cameroon with 108 crew on board on October 12.

The FLNG was converted from a 1975 built Moss LNG carrier with a storage capacity of 125,000 cubic meters by Keppel.

It is designed for a liquefaction capacity of about 2.4 million tons of LNG per annum and will be put in operation for Société Nationale des Hydrocarbures and Perenco Cameroon.

Golar said in its third-quarter report that the next period will see tendering of a notice of readiness, which triggers commissioning rate toll fees.

A ship-to-ship transfer of LNG for commissioning purposes will be undertaken followed by commencement of the full commissioning process.

As part of this process, Golar expects production of first commercial LNG to take place around year end.

Final commissioning of the FLNG is expected to complete during the second part of the first quarter of 2018, Golar said.

LNG World News Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

LNGPorts & LogisticsVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free