Home›Ports & Logistics›Golar expects first LNG from Cameroon FLNG in December
Ports & Logistics

November 30, 2017 · about 8 years ago

Golar expects first LNG from Cameroon FLNG in December

LNG shipper Golar LNG said on Thursday that it expects production of first commercial liquefied natural gas from its FLNG Hilli Episeyo located offshore Kribi in Cameroon to take place around year end. The world’s first FLNG conversion arrived in Cameroon on November 20, and hook-up and connection t

1 minutes read
  • LinkedIn
  • X
  • Email

LNG shipper Golar LNG said on Thursday that it expects production of first commercial liquefied natural gas from its FLNG Hilli Episeyo located offshore Kribi in Cameroon to take place around year end.

The world’s first FLNG conversion arrived in Cameroon on November 20, and hook-up and connection to risers and umbilicals is now underway, according to Golar.

To remind, the FLNG departed Keppel Shipyard on October 1 and left Singapore for Cameroon with 108 crew on board on October 12.

The FLNG was converted from a 1975 built Moss LNG carrier with a storage capacity of 125,000 cubic meters by Keppel.

It is designed for a liquefaction capacity of about 2.4 million tons of LNG per annum and will be put in operation for Société Nationale des Hydrocarbures and Perenco Cameroon.

Golar said in its third-quarter report that the next period will see tendering of a notice of readiness, which triggers commissioning rate toll fees.

A ship-to-ship transfer of LNG for commissioning purposes will be undertaken followed by commencement of the full commissioning process.

As part of this process, Golar expects production of first commercial LNG to take place around year end.

Final commissioning of the FLNG is expected to complete during the second part of the first quarter of 2018, Golar said.

LNG World News Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Ports & LogisticsVessels

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1ADES jack-up rig pair lines up drilling jobs in Nigerian and UK waters
  2. 2Odfjell Drilling’s rig remaining with Norwegian oil & gas operator for another year
  3. 3Karoon boosts Brazilian field’s oil output with all wells now online
  4. 4TotalEnergies offloading Mexican shallow water block to Grupo Carso

Related articles

LNG vessel; Source: GTT
Business & Finance

GTT’s new LR-approved NO96 criteria expand LNG carrier design flexibility

12 days ago

Concept design revealed for Port of Klaipėda’s green methanol bunkering vessel
Business & Finance

Concept design revealed for Port of Klaipėda’s green methanol bunkering vessel

12 days ago

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

LNG vessel; Source: GTT
Business & Finance

GTT’s new LR-approved NO96 criteria expand LNG carrier design flexibility

12 days ago
Concept design revealed for Port of Klaipėda’s green methanol bunkering vessel
Business & Finance

Concept design revealed for Port of Klaipėda’s green methanol bunkering vessel

12 days ago