Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›LNG›ExxonMobil: PNG LNG to remain shut for eight weeks
LNG

March 5, 2018 · about 8 years ago

ExxonMobil: PNG LNG to remain shut for eight weeks

US energy giant ExxonMobil’s Papa New Guinea unit said that it may take approximately eight weeks to repair and restore production at the PNG LNG facility.

1 minutes read
  • LinkedIn
  • X
  • Email

US energy giant ExxonMobil’s Papa New Guinea unit said that it may take approximately eight weeks to repair and restore production at the PNG LNG facility.

To remind, the Papua New Guinea Highlands experienced a 7.5 magnitude earthquake on February 26 , affecting the operations at the export plant.

The unit’s managing director, Andrew Barry said the “the initial rapid response by our well-trained workforce, coupled with controlled emergency shut-down systems, safely shut in our facilities, minimizing damage to equipment and ensuring there was no release of hydrocarbons.”

Work at the Hides gas conditioning plant has turned to restoring camp and associated facilities, the company said on Monday.

While the gas conditioning plant was safely shut in, there has been some damage to various pieces of equipment and foundation supports that will need to be inspected and repaired. Initial visual inspections of the major processing equipment indicate that they have not been significantly impacted, the statement reads.

Surveillance of the pipeline conducted on 28 February confirmed it has not been damaged.

The wells remain safely shut in. A detailed inspection of some well pads has been hampered by earthquake-related impacts to the roads. It is hoped this work can be completed within the next week.

ExxonMobil PNG has also brought forward scheduled maintenance activity at the LNG plant and has redeployed maintenance and support staff from the Hides gas conditioning plant to assist.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

LNGPorts & Logistics

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free