Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Energinet Resumes Kriegers Flak Onshore Cabling Works After Winter Break
Wind Farms

April 4, 2018 · about 8 years ago

Energinet Resumes Kriegers Flak Onshore Cabling Works After Winter Break

Energinet has resumed onshore cable installation works for the Kriegers Flak offshore wind farm after the winter break, and is now ready to start with the final stage of cable excavation on land.

1 minutes read
  • LinkedIn
  • X
  • Email

Energinet has resumed onshore cable installation works for the Kriegers Flak offshore wind farm after the winter break, and is now ready to start with the final stage of cable excavation on land.

In 2016, the onshore cable installation began at Rødvig, where the subsea export cable landed , and continued towards Bjæverskov during the campaigns in the autumn of 2016 and spring and summer 2017.

Now, cable burial will take place between Bjæverskov and Ishøj during April and May, and between Ishøj and Hovegård from May to July.

“During spring and summer 2018 we will bury the last 50km of cables from Bjæverskov over Ishøj and on to Hovegård,” said Martin Johansen , senior project manager at Energinet.

Johansen further added that Energinet is in close dialogue with its contractors to minimise the inconvenience to the local residents as much as possible. “Although we strive to do the job with as little inconvenience to local residents and landowners as possible, there will unfortunately be periods where there will be noise and extra traffic in the area.”

The 600MW Kriegers Flak wind farm consists of two sections, each with its own substation: the 200MW Kriegers Flak A (west section) and the 400MW Kriegers Flak B (east section).

Swedish energy company Vattenfall is building the 600MW offshore wind farm in the Danish part of the Baltic Sea, after winning the tender in November 2016.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free