Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Rampion Team Replacing Faulty Export Cables
Wind Farms

May 11, 2018 · about 8 years ago

Rampion Team Replacing Faulty Export Cables

Although the Rampion offshore wind farm is at a stage of looking at full commissioning, the project site recently saw boulder clearance and UXO identification works starting along one of its export cable routes, since the Rampion team has been replacing the initially installed export cables after id

1 minutes read
  • LinkedIn
  • X
  • Email

Although the Rampion offshore wind farm is at a stage of looking at full commissioning, the project site recently saw boulder clearance and UXO identification works starting along one of its export cable routes, since the Rampion team has been replacing the initially installed export cables after identifying issues that would have affected the wind farm’s performance and longevity.

The new Rampion export cable sections are being installed along the route running between the offshore substation and landfall at Brooklands. The original export cables are not being removed (and replaced) in their entirety, a spokesperson for the project told Offshore WIND.

A new section of the eastern export cable (CR3) has already been installed, while the installation of a new western cable section (CR4) will take place during the summer months.

The CR4 route is the one where the preparation works for cable replacement are now ongoing , carried out by vessels Edda Fonn and Voe Vanguard. The vessels are expected to be working on clearing the route until early June.

The installation of the new part of the eastern export cable was completed at the end of April with burial works done by the trenching vessel Grand Canyon.

According to the spokesperson for the project, the 400MW offshore wind farm remains on schedule to be completed and fully operational later this year.

Offshore WIND Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free