Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Balticconnector Blasting Work About to Begin
Dredging

July 18, 2018 · about 8 years ago

Balticconnector Blasting Work About to Begin

Baltic Connector Oy said in its latest release that the excavation works for the Balticconnector project were completed earlier this week. According to the official announcement, in the following days, the operations will continue with blasting work in the outer archipelago, around 20 kilometers fro

1 minutes read
  • LinkedIn
  • X
  • Email

Baltic Connector Oy said in its latest release that the excavation works for the Balticconnector project were completed earlier this week.

According to the official announcement, in the following days, the operations will continue with blasting work in the outer archipelago, around 20 kilometers from the shore.

“ By beginning preparatory work in July, we were able to save enough time for planning so that the work can be carried out safely and with equipment appropriate for the level of difficulty of the work. The timing is optimal also because it means we can avoid the hazards brought on by autumn storms ,” said Baltic Connector’s Project Director, Tom Främling.

The blasting work will include three phases:

“ Excavation work in the area will be carried out 24/7 whereas blasting work is limited to daytime between 7 am and 6 pm, ” said Baltic Connector Oy.

The work is estimated to take two weeks and after this, the excavation work will continue in the area of Inkoo fairway and Lillskämmö.

The Balticconnector project will comprise the offshore pipeline between Inkoo in Finland and Paldiski in Estonia, and the Finnish and Estonian onshore pipelines that will link Balticconnector to the existing gas transmission networks in these countries.

The route covers 21 kilometers of onshore pipeline in Finland, 77 kilometers of offshore pipeline, and 55 kilometers of onshore pipeline in Estonia.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free