Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›H&L Contracting Wins Saco River Dredging Deal
Dredging

November 21, 2018 · about 7 years ago

H&L Contracting Wins Saco River Dredging Deal

Maintenance dredging of a portion of the Saco River Federal navigation project (FNP) in Biddeford and Saco, Maine, will be completed under the terms of a $3.9 million contract issued recently by the U.S. Army Corps of Engineers, New England District. The dredging work, to be accomplished by H&L Cont

2 minutes read
  • LinkedIn
  • X
  • Email

Maintenance dredging of a portion of the Saco River Federal navigation project (FNP) in Biddeford and Saco, Maine, will be completed under the terms of a $3.9 million contract issued recently by the U.S. Army Corps of Engineers, New England District.

The dredging work, to be accomplished by H&L Contracting, Inc. LLC, of Bay Shores, New York, is scheduled to start in mid-December 2018 and take about 3 months to complete.

“ The project consists of hydraulically dredging a portion of the Federal navigation channel at the mouth of the Saco River which includes an 8-foot deep entrance channel and three 6-foot deep anchorages,” said Project Manager Craig Martin , of the Corps’ New England District, Programs/Project Management Division in Concord, Massachusetts.

Approximately 41,000 cubic yards of required dredging, with another 36,000 cubic yards of 1-foot allowable over depth dredging would bring these areas back to their authorized dimensions. Sandy shoal material dredged from the mouth of the river will be pumped approximately 8,000 feet north to Camp Ellis Beach.

Additionally, a contract option to mechanically dredge a portion of the FNP’s 8-foot deep channel and 6-foot deep maneuvering basin at the city center in Saco is included.

Approximately 22,000 cubic yards of required, and another 13,000 cubic yards of 1-foot allowable over depth dredging of predominantly fine grain sand and silty shoal material will be completed by mechanical dredge and hauled 1.25 miles south to a previously used in-river placement site for disposal.

Dredging and disposal operations will be performed between Nov. 15, 2018 and March 15, 2019 to meet environmental time of year restrictions.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free