Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Phase 1 of the Arundel Tidal Defense Scheme Underway
Dredging

November 30, 2018 · about 7 years ago

Phase 1 of the Arundel Tidal Defense Scheme Underway

The Environment Agency contractors have started engineering surveys of the river defenses in Arundel under the phase 1 of the tidal defense scheme. According to the EA, contractors will be working on and near the River Arun for a number of days over a 12 week period. These surveys include drone surv

1 minutes read
  • LinkedIn
  • X
  • Email

The Environment Agency contractors have started engineering surveys of the river defenses in Arundel under the phase 1 of the tidal defense scheme.

According to the EA, contractors will be working on and near the River Arun for a number of days over a 12 week period.

These surveys include drone surveys from the air, visual inspections on foot and ‘scraping’ of sheet steel piles on the River Road side by boat (to measure their thickness).

On 19 November 2018 the contractors started to dig small boreholes in 8 locations along the river banks in Arundel. This is so that the material below the ground can be analysed, to gain a better understanding of the stability of the engineered river defenses over the long-term, reported the Environment Agency.

All these engineering surveys will help the Environment Agency to understand the condition of the defenses and assist them in preparing a preferred design option for the scheme.

The EA also added that repairs to the collapsed wall at River Road will be completed first, and work there is scheduled to begin by autumn 2019. The whole phase 1 scheme is estimated to be completed by autumn 2020.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free