Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Sebastian Inlet Dredging Moves Ahead
Dredging

February 20, 2019 · about 7 years ago

Sebastian Inlet Dredging Moves Ahead

Dredging works to remove approximately 150,000 cubic yards of sand from the Sebastian Inlet in Florida are moving ahead, Sebastian Inlet District said in its latest announcement. Ferreira Construction of Stuart, Florida, has been using its 18-inch hydraulic dredger Lori Hill, equipped with Hypack so

1 minutes read
  • LinkedIn
  • X
  • Email

Dredging works to remove approximately 150,000 cubic yards of sand from the Sebastian Inlet in Florida are moving ahead, Sebastian Inlet District said in its latest announcement.

Ferreira Construction of Stuart, Florida, has been using its 18-inch hydraulic dredger Lori Hill, equipped with Hypack software, to remove sand from the inlet’s sand trap and navigation channel.

At the beginning of this month, approximately 10,000 cubic yards of sand have been placed and crews will work their way South, anticipated to progress approximately 1,000 feet a week for the next 5-6 weeks depending on weather conditions.

According to Michael Ciabatteri, project manager for Ferreira, sand is moving through about 18,000 feet of 18-inch HDPE pipe with the two inline boosters, a 16- and an 18-inch, one placed under a bridge and one on the beach.

Dredging of the sand trap for beach placement as a priority started in January, and will continue through February 25. The final beach tilling and grading are set to be complete by the end of February, the district said.

Dredging of the channel will begin in mid-March, filling the DMMA with sand, before demobilization in mid-April.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Saipem hands Saudi jack-up fleet to ADES in strategic shallow-water exit
  2. 2Valeura advances Gulf of Thailand expansion with PTTEP farm-in approval
  3. 3Santos broadens Asia-Pacific LNG portfolio with Canadian supply and 10-year POSCO deal
  4. 4Borr Drilling keeps three jack-up rigs as it reorganizes Mexico ops with stake sale

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free