Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›DPWH Kicks Off Manila Bay Dredging
Dredging

March 5, 2019 · about 7 years ago

DPWH Kicks Off Manila Bay Dredging

The Government of Philippines’ Department of Public Works and Highways (DPWH) today officially started the Manila Bay dredging operations – from the Manila Yacht Club breakwater to the United States Embassy in Manila. Under the project, approximately 225,000m³ of silt is set to be removed from the m

1 minutes read
  • LinkedIn
  • X
  • Email

The Government of Philippines’ Department of Public Works and Highways (DPWH) today officially started the Manila Bay dredging operations – from the Manila Yacht Club breakwater to the United States Embassy in Manila.

Under the project, approximately 225,000m³ of silt is set to be removed from the mentioned areas, the Philippine News Agency (PNA) reported today.

DPWH Secretary, Mark Villar , said that the heavy equipment composed of amphibious excavators, dumping scows, dump trucks, debris segregator, street sweepers and vacuum sewer jet cleaners are deployed in the area and other strategic locations for the cleanup operations.

This event marks the full-blast dredging within this critical section of Manila Bay. The Bureau of Equipment (BOE), Regional and District Engineering Offices in Metro Manila have deployed a total of 28 machines and 50 personnel to operate 16 hours a day, six days a week, said the secretary during the launching of the Manila dredging program.

“Excavation will be the major mechanism for the removal of the accumulated pollutants in Manila Bay. Through our hardworking crew and equipment fleet, we aim to de-silt within 150 meters from the shoreline of Manila Bay,” Villar said.

DPWH-BOE Director, Toribio Noel Ilao, added that implementation of de-silting activities will be divided into five sectors, each ranging from 200m to 300m long, until the entire 1.5km is finished.

Each sector will be de-silted approximately within 90 to 120 days.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Saipem hands Saudi jack-up fleet to ADES in strategic shallow-water exit
  2. 2Valeura advances Gulf of Thailand expansion with PTTEP farm-in approval
  3. 3Santos broadens Asia-Pacific LNG portfolio with Canadian supply and 10-year POSCO deal
  4. 4Borr Drilling keeps three jack-up rigs as it reorganizes Mexico ops with stake sale

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free