Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›First Triton Knoll Onshore Cables Roll Out
Wind Farms

March 22, 2019 · about 7 years ago

First Triton Knoll Onshore Cables Roll Out

The first onshore electrical cables destined for the Triton Knoll offshore wind farm have rolled out from production and are heading towards the Port of Boston, the UK. The High Voltage Alternating Current (HVAC) cables will make up the onshore cable network, connecting power from the 860MW offshore

1 minutes read
  • LinkedIn
  • X
  • Email

The first onshore electrical cables destined for the Triton Knoll offshore wind farm have rolled out from production and are heading towards the Port of Boston, the UK.

The High Voltage Alternating Current (HVAC) cables will make up the onshore cable network, connecting power from the 860MW offshore wind farm to the new onshore substation at Bicker Fen.

According to Triton Knoll, this milestone marks the delivery of the first major elements of the project’s onshore electrical system and will be ready for installation along the cable route in the summer.

The cables are being delivered to the port on 28 cable drums, typically 4.5m x 3.5m in size, with the majority expected to arrive on 24 March.

The drums will then be transported on heavy goods vehicles, via the A16 to a secure storage compound near to the project’s cable route, Triton Knoll said.

Each cable drum weighs between 17 to 26t and contains between 1,023m to 1,690m of HVAC cable. In total there are 306 cable drums required for the entire onshore cable route, which adds up to more than 360km of cable.

The Triton Knoll offshore wind farm, being developed by Innogy Renewables UK Ltd, in partnership with J-Power and Kansai Electric Power, will comprise 90 MHI Vestas 9.5MW turbines scheduled to be operational in 2021.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Saipem hands Saudi jack-up fleet to ADES in strategic shallow-water exit
  2. 2Valeura advances Gulf of Thailand expansion with PTTEP farm-in approval
  3. 3Santos broadens Asia-Pacific LNG portfolio with Canadian supply and 10-year POSCO deal
  4. 4Borr Drilling keeps three jack-up rigs as it reorganizes Mexico ops with stake sale

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free