Offshore Energy
  • news
  • test
JobsNewsletter
Offshore Energy logo
Topics
  • News
  • Contracts & Tenders
  • Authorities & Government
  • Automation
  • Business & Finance
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Parkwind, Jan De Nul Begin Seabed Works for Northwester 2
Operations & Maintenance

July 19, 2019 · about 7 years ago

Parkwind, Jan De Nul Begin Seabed Works for Northwester 2

Parkwind and Jan De Nul Group have started offshore seabed preparation works for the 219 MW Northwester 2 offshore wind farm. The works mark the start of construction of the offshore wind farm off the Belgian coast. The Northwester 2 wind farm will count 23 V164-9.5MW MHI Vestas offshore wind turbin

2 minutes read
  • LinkedIn
  • X
  • Email

Parkwind and Jan De Nul Group have started offshore seabed preparation works for the 219 MW Northwester 2 offshore wind farm.

The works mark the start of construction of the offshore wind farm off the Belgian coast.

The Northwester 2 wind farm will count 23 V164-9.5MW MHI Vestas offshore wind turbines and will be the first project to ever install this model. The turbines on monopile foundations will link through an offshore high voltage station to Elia’s Offshore Switch Yard (OSY) to export its electricity.

As of 2020, the Northwester 2 wind farm will power approximately 220,000 households in Belgium.

The project will introduce a new design for the external access platforms on the foundations – the box platform. The platform, developed and patented by Parkwind, consists only of steel plate material.

Peter Caluwaerts , project director Northwester 2 at Parkwind said: “At Parkwind, we continuously look for optimizations and cost-effective solutions while developing offshore wind farms. The box platform is a show case of this attitude. Indeed, this innovative design reduces the overall cost of the foundation fabrication by introducing ship building techniques in the fabrication process. Moreover, the box platform simplifies and reduces offshore maintenance activities over the lifetime of the wind farm. It is great to see the initial ideas now coming to life at the start of the offshore construction works.”

In addition, Jan De Nul Group has finished the offshore scour protection works on the different wind turbine locations. At each location, Jan De Nul Group’s subsea rock installation vessel Simon Stevin has installed a 32 m diameter wide and 700 mm thick rock layer to stabilize the seabed around the foundation.

Jan De Nul Group is now gearing up to install the first foundation in the coming days. The monopile foundations for the wind turbines will be hammered directly through the rock layer into the seabed.

Stan Logghe , senior project manager Northwester 2 at Jan De Nul Group, said: “A full year of preparation is now coming to an end with the start of the construction phase. With the installation vessel Vole au vent returned to Ostend, Jan De Nul is now ready to commence the installation of the foundations for the Northwester 2 wind farm.”

Jan De Nul Group equipped its Vole au vent with the advanced monopile gripper, delivered by Huisman. Jan De Nul Group will deploy this gripper for the first time on the Northwester 2 project.

Northwester 2 shareholders include Parkwind (70%) and Japanese Sumitomo Corporation (30%).

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Operations & Maintenance

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1ADES jack-up rig pair lines up drilling jobs in Nigerian and UK waters
  2. 2Odfjell Drilling’s rig remaining with Norwegian oil & gas operator for another year
  3. 3Karoon boosts Brazilian field’s oil output with all wells now online
  4. 4TotalEnergies offloading Mexican shallow water block to Grupo Carso

Related articles

FPSO Cidade de Itajai is operating on the Baúna field - Karoon
Business & Finance

Brazilian oil project back in production mode after 28-day shutdown

about 2 months ago

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

FPSO Cidade de Itajai is operating on the Baúna field - Karoon
Business & Finance

Brazilian oil project back in production mode after 28-day shutdown

about 2 months ago