Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›Northwester 2 Turbines to Feature 27-Year Maintenance-Free Fasteners
Offshore Wind

November 6, 2019 · about 6 years ago

Northwester 2 Turbines to Feature 27-Year Maintenance-Free Fasteners

Northwester 2 turbines will be secured to their foundations with super duplex fasteners designed to be maintenance-free throughout the 27-year turbine design life. The stainless studs, nuts and washers for the 219MW Belgian offshore wind farm have been delivered to Bladt Industries by Swedish manufa

2 minutes read
  • LinkedIn
  • X
  • Email

Northwester 2 turbines will be secured to their foundations with super duplex fasteners designed to be maintenance-free throughout the 27-year turbine design life.

The stainless studs, nuts and washers for the 219MW Belgian offshore wind farm have been delivered to Bladt Industries by Swedish manufacturer BUMAX under a SEK 1.7 million (approx. EUR 160,000) contract.

The prerequisites for the fasteners were that they have a high degree of corrosion resistance and low maintenance requirements to ensure cost-efficiency, less turbine downtime and to reduce the need for stud replacement.

According to the manufacturer, the custom-made fasteners for Northwester 2 have high corrosion resistance and are suitable for challenging North Sea conditions, where they will be affected by saltwater that might cause corrosion problems when salt particles dry on the studs.

Furthermore, the studs also have a very high tensile strength to maintain the integrity of a turbine throughout its lifespan.

BUMAX said that it had delivered the Northwester 2 order in a tight delivery deadline, reducing the normal production schedule for these kinds of fasteners by several weeks to avoid any potential delays to the project.

The 219MW offshore wind farm, currently under construction some 50km north-west of Oostende, will comprise 23 MHI Vestas 164-9.5MW turbines placed on top of monopile foundations delivered by Bladt Industries.

The first of the 23 foundations was installed at the site on 30 July, within one month after the start of the offshore construction works. Northwester 2 is scheduled for commissioning in 2020.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Saipem hands Saudi jack-up fleet to ADES in strategic shallow-water exit
  2. 2Valeura advances Gulf of Thailand expansion with PTTEP farm-in approval
  3. 3Santos broadens Asia-Pacific LNG portfolio with Canadian supply and 10-year POSCO deal
  4. 4Borr Drilling keeps three jack-up rigs as it reorganizes Mexico ops with stake sale

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free