Home›Dredging›USACE Plans Shoreline Protection Project at Pleasant Point Reservation
Dredging

December 23, 2019 · about 6 years ago

USACE Plans Shoreline Protection Project at Pleasant Point Reservation

The U.S. Army Corps of Engineers, New England District, has just announced a plan to stabilize approximately 1,500 feet of shoreline that is eroding at the Pleasant Point Reservation near Perry, Maine. The work is being implemented under the Section 14 Emergency Shoreline Protection program. The Ple

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, New England District, has just announced a plan to stabilize approximately 1,500 feet of shoreline that is eroding at the Pleasant Point Reservation near Perry, Maine.

The work is being implemented under the Section 14 Emergency Shoreline Protection program. The Pleasant Point Reservation is home to members of the federally recognized Passamaquoddy Tribe.

The purpose of the proposed emergency shoreline protection project is to prevent ongoing shoreline erosion in front of tribal housing, a church, and a senior center at the Pleasant Point Reservation in Washington County, Maine by constructing a 1,500-foot long revetment.

Tribal owned-facilities may be at risk from further erosion unless immediate action is taken to stabilize the shoreline, said USACE.

The 1,500-foot long and 36-foot wide stone revetment design consists of a geotextile fabric overlain by a 6- inch layer of gravel stone, a 12-inch thick double layer of underlayer stone, and a 27-inch thick double layer of 1.0 ton armor stone on a IV: 2H slope.

Construction is expected to take four to six months and will be completed during the low portion of the tidal cycle. The proposed revetment will tie into the southern section of a newly constructed 300-foot revetment in front of the tribal owned Waste Water Treatment Plant.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1SED Energy Holdings and Ventura Offshore to unite into one
  2. 2New Boskalis rock installation vessel starts work offshore Poland
  3. 321 companies apply for Norway’s new oil & gas exploration areas
  4. 4Spanish shipyard launches its largest-ever vessel, built for Østensjø Rederi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free