Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›Able Seaton Port Starts Preparing for Triton Knoll Ops
Offshore Wind

February 4, 2020 · about 6 years ago

Able Seaton Port Starts Preparing for Triton Knoll Ops

Works on enabling Able Seaton Port for Triton Knoll wind turbine pre-assembly have begun, including preparing the existing site, establishing new drainage and upgrading the internal electricity supply.

1 minutes read
  • LinkedIn
  • X
  • Email
Dorian LPG takes over newbuild dual-fuel LPG and ammonia gas carrier
PPF; Source: ConocoPhillips

Works on enabling Able Seaton Port for Triton Knoll wind turbine pre-assembly have begun, including preparing the existing site, establishing new drainage and upgrading the internal electricity supply.

In the coming months, the construction teams will build new infrastructure: access roads, office buildings and accommodation for a project team of around 50 people.

Turbine handling equipment will be set up at the port later in the year.

Teesside’s Able Seaton Port will house the pre-assembly of MHI Vestas 9.5MW wind turbines, with the first components due to arrive later in 2020. The 89-meter turbine towers, 80-meter turbine blades and the 375-tonne nacelles will be prepared for transport and installation at the offshore site in 2021.

Construction of the 875MW offshore wind farm, comprising 90 wind turbines, is already underway. The first foundation was installed in January 2020.

In 2021, installation and energization of wind turbines will be taking place. The first electricity is expected to flow into the UK National Grid later that year.

Able Seaton Port was selected by MHI Vestas Offshore Wind as the Triton Knoll offshore wind turbine pre-assembly base in 2018. The Triton Knoll project company and MHI Vestas are jointly investing in the works at the Teesside facility.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindPorts & Logistics

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free