Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Living Stone starts wiring SeaMade array
Cabling

April 14, 2020 · about 6 years ago

Living Stone starts wiring SeaMade array

DEME’s cable installation vessel Living Stone has started the inter-array cabling work at the SeaMade offshore wind farm.

1 minutes read
  • LinkedIn
  • X
  • Email
Living Stone cable installation vessel at sea, with wind turbines in the background
Photo source: DEME Group

The cable installation vessel Living Stone has commenced the inter-array cabling work at the SeaMade offshore wind farm.

The cable load-out took place in Hartlepool, UK, where the cable supplier JDR Cable Systems is based.

JDR signed a contract with DEME, which is in charge of installing the cables, in June 2019. The contract includes the delivery of 78.1 kilometres of aluminium core inter-array cables, as well as cable accessories.

The 33 kV cable system, connecting the wind farm’s 58 Siemens Gamesa 8.4 MW turbines, will carry the electricity to SeaMade’s two offshore substations. The offshore substations will convert the electricity from 33 kV to 220 kV and export it into the grid via Elia’s Modular Offshore Grid (MOG).

DEME has also been in charge of the installation of the export cable. The Living Stone completed the export cable works in December 2019.

The Innovation vessel put the final foundation in place on 2 January. Also, both of SeaMade’s offshore substations have been in place since mid-March. The wind turbine installation , which has been assigned to DEME’s installation vessel Apollo, is expected to start soon.

“COVID-19 is a tough stretch for our teams at sea and on shore, but we keep going as One DEME, One Team” , DEME stated via social media.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingGridOffshore WindBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free