LOGIC: The standard form contracts, including the 2004 General Conditions of Contract for Marine Construction and the recent 2018 General Conditions of Contract for Offshore Decommissioning, all contain an exhaustive list of possible FM events which does not include “pandemic” or anything relating to illness and disease. As such, unless the wording has been amended, Covid-19 and its consequences will not be sufficient to trigger this clause (subject, however, to the change in law provision dealt with further below). If changes to the wording have been made, it is important to note that LOGIC also explicitly requires a causal connection between the relevant event and the failure to perform, which must be demonstrated by the party seeking to rely on it. Notice is usually stated to be required “without delay”, the precise nature of which will be highly fact specific.