Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›Calcasieu Pass LNG’s second tank roof lifted
News

May 20, 2020 · about 6 years ago

Calcasieu Pass LNG’s second tank roof lifted

Venture Global LNG raised the second LNG storage tank roof at the company’s Calcasieu Pass LNG export facility in Cameron Parish, Louisiana.

1 minutes read
  • LinkedIn
  • X
  • Email
Calcasieu Pass LNG's second tank roof lifted
Image courtesy of Venture Global LNG

Venture Global LNG raised the second LNG storage tank roof at the company’s Calcasieu Pass LNG export facility in Cameron Parish, Louisiana.

This major project milestone was completed nearly three months ahead of schedule and comes a mere nine months after the project’s final investment decision (FID).

The contactor air raised the 1.8 million pound tank dome and assembly into place on Tuesday, May 19, less than a month after the raising of the first LNG tank roof on April 24 .

The tank dome was raised in one hour and 20 minutes using 0.25 psi of pressure, Venture Global said in its statement.

CB&I Storage Tank Solutions, a division of McDermott International, is constructing the project’s dual 200,000-cbm tanks.

First combined cycle plant modules arrive

Venture Global also received the first modules for the export facility’s 720 MW combined cycle gas turbine power plant at the site.

The contractor has already installed key components of the gas-insulated switchgear (GIS). The site has also begun receiving and setting modules for the air-cooled condenser (ACC).

To remind, the Calcasieu Pass facility is under construction at the intersection of the Calcasieu Ship Channel and the Gulf of Mexico.

Once fully built it will have a 10 mtpa LNG production capacity.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

News

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free