Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Foundations›Equinor and Polenergia start gauging Polish offshore wind supply chain potential
Foundations

October 5, 2020 · about 6 years ago

Equinor and Polenergia start gauging Polish offshore wind supply chain potential

Polenergia S.A. and Equinor have started preparations to develop the supply chain for the two offshore wind projects in the Polish Baltic Sea with a combined capacity of 1.44 GW. Polenergia and Equinor hold 50 per cent stakes each in MFW Bałtyk II Sp. z o.o. and MFW Bałtyk III Sp. z o.o., the specia

1 minutes read
  • LinkedIn
  • X
  • Email
Equinor and Polenergia start gauging Polish offshore wind supply chain potential
Equinor

Polenergia S.A. and Equinor have started preparations to develop the supply chain for the two offshore wind projects in the Polish Baltic Sea with a combined capacity of 1.44 GW.

Polenergia and Equinor hold 50 per cent stakes each in MFW Bałtyk II Sp. z o.o. and MFW Bałtyk III Sp. z o.o., the special purpose companies developing the Bałtyk II and Bałtyk III offshore wind projects.

The 720 MW Bałtyk II and the 720 MW Bałtyk III wind farm are located in areas approximately 27 and 40 kilometres from the port of Łeba in water depths of 20-40 metres.

Equinor will manage the development, construction, and operational phases of the two projects.

The developers will hold a series of online workshops in October to familiarize Tier 1 contractors with the local supply chain.

In total, four workshops will be held from 21 to 29 October each focussing on a different segment: wind turbines, foundations, electrical systems including onshore substations, and offshore substations.

The Bałtyk III wind farm is expected to deliver first power in 2025 and Bałtyk II in 2027.

Polenergia and Equinor are also jointly developing the 1,560 MW Bałtyk I offshore wind project.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

FoundationsGridOffshore WindTurbinesWind FarmsBusiness & FinanceBusiness Developments & Projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free