Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Deepwater Installation›NKT Victoria wraps up Moray East OWF export cable work
Deepwater Installation

October 13, 2020 · about 6 years ago

NKT Victoria wraps up Moray East OWF export cable work

All three export cables for the Moray East offshore wind farm have been laid and pulled in, with the cable laying vessel NKT Victoria now demobilised after finishing the project. The vessel Havila Phoenix is currently burying the three subsea power cables below the seabed by using remotely operated

1 minutes read
  • LinkedIn
  • X
  • Email
The NKT Victoria vessel at sea
NKT; The NKT Victoria vessel

All three export cables for the Moray East offshore wind farm have been laid and pulled in, with the cable laying vessel NKT Victoria now demobilised after finishing the project.

The vessel Havila Phoenix is currently burying the three subsea power cables below the seabed by using remotely operated trenching vehicles. Cable trenching is expected to be ongoing until early November, and will be followed by a separate campaign to install remedial protection over the cables on any remaining unburied and unprotected sections, according to the project’s latest Notice of Operations.

Offshore construction at the project site located some 22 kilometres off the Aberdeenshire is progressing with other wind farm components as well.

So far, 42 wind turbine foundations have been installed by Seajacks Scylla and the inter-array cable installation work is now well underway.

Cable pull-ins and free lay of inter-array cables between wind turbine locations are being carried out by the Living Stone cable laying vessel, supported by Grand Canyon and Deep Cygnus vessels which are providing walk-to-work system for the operations.

The inter-array cable installation will be carried out in three campaigns. This first campaign started on 29 September and is expected to be completed by the end of November.

Moray East, whose three offshore transformer modules (OTMs) have been in place since mid-September, will feature 100 MHI Vestas 9.5 MW wind turbines.

The offshore wind farm is scheduled to be commissioned in 2022.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Deepwater InstallationGridOffshore WindSubseaWind FarmsBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free