Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Osprey Group bags Moray East OWF contract
Cabling

November 20, 2020 · about 5 years ago

Osprey Group bags Moray East OWF contract

The Osprey Group has won a contract to provide handling and storage services for the spare export cable for the Moray East offshore wind farm. Under the contract, the company will receive and store approximately 2,500 metres of subsea cable and approximately 1,500 metres of HDD cable to be received

1 minutes read
  • LinkedIn
  • X
  • Email
Osprey Group team in front of a cable basket at Port of Sunderland
Osprey Group

The Osprey Group has won a contract to provide handling and storage services for the spare export cable for the Moray East offshore wind farm.

Under the contract, the company will receive and store approximately 2,500 metres of subsea cable and approximately 1,500 metres of HDD cable to be received from NKT’s cable laying vessel NKT Victoria by the end of this year.

Osprey will use a powered quadrant and self-propelled modular transporters to load the cable into the basket at the Port of Sunderland, where it will be stored for at least two years.

“These cabling baskets are a specialist item, we get them built to our own design. For this contract, we’ve been working with fabricators JW Colpitts, and the Port of Sunderland” , said Pete Fletcher , Osprey Director.

NKT Victoria has installed all three Moray East export cables by mid-October and currently, the first campaign for inter-array cable testing and termination is underway at the site.

NKT signed a firm contract for the supply and installation of the wind farm’s export cables at the end of 2018.

Moray East, whose three offshore transformer modules (OTMs) have been in place since mid-September, will feature 100 MHI Vestas 9.5 MW wind turbines.

The offshore wind farm is scheduled to be commissioned in 2022.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingOffshore WindSubseaWind FarmsBusiness & FinanceBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free