Home›Authorities & Government›Audit finds improvement points for Neptune at Fenja project
Authorities & Government

December 3, 2020 · about 5 years ago

Audit finds improvement points for Neptune at Fenja project

Norwegian offshore safety watchdog has found a couple of improvements points at Neptune Energy’s Fenja project development located offshore Norway.

2 minutes read
  • LinkedIn
  • X
  • Email
Fenja project - Neptune

Norwegian offshore safety watchdog has found a couple of improvements points at Neptune Energy’s Fenja project development located offshore Norway.

Earlier this week, the Petroleum Safety Authority (PSA) said it had carried out an audit of Neptune Energy and its project management and project follow-up for the Fenja project.

The audit was conducted on 30 September 2020.

The objective of the audit was to verify that, in its project management, Neptune is ensuring that it is reducing risk in the project execution phase and preventing accidents during start-up and operation.

No non-conformities were detected during the audit. However, two improvement points were detected relating to the follow-up of elements in the management system and the dissemination of information and reporting.

The safety authority has asked for the company’s assessment of the observations it has categorized as improvement points. The reply deadline is set for 21 December 2020.

Neptune took over the operatorship of the Fenja field back in December 2018.

Fenja is Neptune’s first operated development project on the Norwegian Shelf and is estimated to contain 97 million boe.

Located in the Norwegian Sea 120 kilometres north of Kristiansund and at a water depth of 320 metres, the Fenja field will be developed as a subsea tie-back to the Njord-A platform.

Neptune kicked off its Fenja drilling campaign following the spud of the first well in April 2020.

The drilling program for 2020 includes two top holes and two geo-pilots, with an expected duration of 85 days. It is being carried out by the West Phoenix drilling rig, operated by Seadrill.

In September 2020, Neptune started drilling the Bue well on the Fenja field. Bue is, along with Pil, one of the discoveries on the Fenja field.

Pil is being developed first, with two subsea templates tied back to the Njord A platform for processing and export.

Production start-up at Fenja is expected in the fourth quarter of 2021.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Authorities & GovernmentBusiness Developments & ProjectsExploration & ProductionOperations & MaintenanceRegulation & PolicyRules & RegulationSafety

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1ADES jack-up rig pair lines up drilling jobs in Nigerian and UK waters
  2. 2Odfjell Drilling’s rig remaining with Norwegian oil & gas operator for another year
  3. 3Karoon boosts Brazilian field’s oil output with all wells now online
  4. 4TotalEnergies offloading Mexican shallow water block to Grupo Carso

Related articles

Illustration; Source: TotalEnergies
Business & Finance

TotalEnergies offloading Mexican shallow water block to Grupo Carso

10 days ago

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Illustration; Source: TotalEnergies
Business & Finance

TotalEnergies offloading Mexican shallow water block to Grupo Carso

10 days ago