Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Skye-Harris subsea cable replacement all done
Cabling

September 2, 2021 · about 5 years ago

Skye-Harris subsea cable replacement all done

Scottish and Southern Electricity Networks (SSEN) Distribution has completed the replacement of the submarine electricity distribution cable between Skye and Harris, following a cable fault in October last year. SSEN Distribution connected and energised the new cable on 31 August before gradually re

2 minutes read
  • LinkedIn
  • X
  • Email
Skye-Harris subsea cable replacement all done
SSEN

Scottish and Southern Electricity Networks (SSEN) Distribution has completed the replacement of the submarine electricity distribution cable between Skye and Harris, following a cable fault in October last year.

SSEN Distribution connected and energised the new cable on 31 August before gradually returning the network to normal operation and reconnecting Lewis and Harris to the mainland electricity network.

The £28 million cable replacement project involved offshore works using vessels Maersk Connector and Grand Canyon 3, working with principal contractor Global Offshore to install and protect the 33 kV cable between Ardmore, Skye and Beacravik in Harris.

The project also included onshore works at each shore end to connect the new cable to the existing electricity network and restore local beaches at Ardmore and Beacravik to their natural state.

Since October, Battery Point and Arnish Power Stations on Lewis have been running at full-duty operation, alongside on-island renewable generation. These stations will now return to backup operation.

To remind, China’s Ningbo Orient Cable (NBO) provided the replacement cables for the project under a contract secured at the end of last year.

SSEN Distribution is currently assessing the future resilience and electricity demand needs for customers and communities on Lewis and Harris. This includes liaison with SSEN Transmission on its proposed 600 MW HVDC transmission link to the Western Isles, which remains subject to developer commitment and regulatory approval.

A third-party study will be carried out prior to the final business plan submission in December to assess options, including the installation of a second 33 kV cable between Skye and Harris, if the current transmission needs case is not taken forward. All plans will be subject to regulatory approval.

Related Articles

Cabling

Skye-Harris subsea cable replacement campaign at full throttle

1 min read

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingSubseaBusiness Developments & ProjectsOperations & MaintenanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1TotalEnergies, Staatsolie and APA advancing $12.2B oil project ahead of 2027 drilling ops
  2. 2New gas discovery springs up from India’s frontier deepwater basin
  3. 3Legal showdown underway as Cotemar moves to freeze almost $60M in American Bureau of Shipping subsidiary’s assets
  4. 4Jan De Nul orders another newbuild trenching support vessel

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free