Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Norwegian authorities give go-ahead for Equinor’s North Sea electrification project
Fossil Energy

December 21, 2021 · about 4 years ago

Norwegian authorities give go-ahead for Equinor’s North Sea electrification project

Norwegian Ministry of Petroleum and Industry has approved a plan for the development and operation of Equinor’s Troll field in the North Sea.

3 minutes read
  • LinkedIn
  • X
  • Email
Norwegian authorities give go-ahead for Equinor’s North Sea electrification project
Troll C platform; Source: Equinor

Norwegian Ministry of Petroleum and Industry has approved a plan for the development and operation of the Equinor-operated Troll field in the North Sea, which will enable the operator to turn its Troll West electrification plans into reality.

Equinor filed its plan for the Troll West electrification project to Norwegian authorities back in April 2021. The plan includes partial electrification of Troll B and full electrification of the Troll C semi-submersible platforms.

The Ministry of Petroleum and Energy approved the changed plan for the development and operation of the Troll field on Friday, explaining that the operation of the Troll B and C platforms would be changed to full and partial use of power from land, respectively. Troll A is already powered by land.

This project includes an 85-kilometre-long cable from Kollsnes to Troll B, and a 20-kilometre-long cable from Troll B to Troll C. In addition, the approved project includes major and complex modifications to the Troll B and C platforms, while a building will also be built on land at Kollsnes west of Bergen with electrical equipment and landfall for the cable.

According to the Ministry of Petroleum and Energy, the building and excavation work on the land will be established together with the licensees in the Oseberg field. Earlier this year, the ministry granted a license to connect the platforms to the power grid at Kollsnes.

Based on these plans, the new energy solution on Troll B will start in the first quarter of 2024 and the electrification of Troll C is also planned for the first quarter of 2024, while completion is expected in the second quarter of 2026.

According to Equinor’s calculations, the project will reduce CO 2 emissions from Troll by an average of 450,000 tonnes per year. As a result, NO X emissions will be reduced by approximately 1,750 tonnes per year.

The Troll field lies in the northern part of the North Sea, around 65 kilometres west of Kollsnes, near Bergen. The licensees of Troll are Equinor Energy (operator; 30.6 per cent), Petoro (56 per cent), Shell (8.1. per cent), TotalEnergies EP Norge (3.7 per cent) and ConocoPhillips Skandinavia (1.6 per cent).

To remind, following a letter of intent from February 2021, Aker Solutions was awarded an EPCI contract in April. These modifications would enable the Troll B and C topsides to receive power from shore. A few months later, Aker Solutions awarded a contract to Siemens to supply complete packages for the electrical transmission, distribution, and power management system (PMS) for the project.

It is also worth reminding that Equinor and its partners also submitted a plan for the development and operation of another field to the minister of petroleum and energy, Marte Mjøs Persen , in late November.

Related Articles

Fossil Energy

Equinor files plan for further development of North Sea field, unveils investment of over $1.1bn

6 min read

This plan is for the Oseberg field in the northern part of the North Sea and based on Equinor’s statement from 26 November 2021, the Oseberg area partners would reduce CO 2 emissions from the field while increasing gas production.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyOil & GasSubseaAuthorities & GovernmentBusiness & FinanceBusiness Developments & ProjectsEnvironmentExploration & ProductionProject & TendersRegulation & PolicyRules & RegulationTransition

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Halliburton bags Eni’s deepwater bundle as Eastern Mediterranean gas buildout continues
  2. 2TechnipFMC picks up multimillion-dollar subsea scope for Petronas’ deepwater project
  3. 3Southeast Asia’s hydrocarbon push: Valeura hits oil pay, eyes new satellite development
  4. 4FSRU docks in Stade as LNG terminal prepares to feed gas into German grid from November

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free