Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid›Boulder removal services wanted for Ostwind 3
Grid

April 8, 2022 · about 4 years ago

Boulder removal services wanted for Ostwind 3

German offshore transmission system operator (TSO) 50Hertz has issued a tender seeking boulder removal services on the cable route of the Ostwind 3 project. The contract covers, but is not limited to, the provision and operation of all assets necessary for the works, removal of boulders, and reporti

2 minutes read
  • LinkedIn
  • X
  • Email
Boulder removal services wanted for Ostwind 3
50Hertz

German offshore transmission system operator (TSO) 50Hertz has issued a tender seeking boulder removal services on the cable route of the Ostwind 3 project.

The contract covers, but is not limited to, the provision and operation of all assets necessary for the works, removal of boulders, and reporting and interfacing with the employer and other relevant parties.

The aim of the project is to mitigate the risk of the presence of boulders in the cable installation corridor which could possibly hinder the cable installation or damage the cable installation spread.

In addition to the Ostwind 3, the tender also includes possible future projects in the Baltic Sea and North Sea.

Estimated value of the contract excluding VAT is €60 million and the expected duration is six years.

The deadline for the submission of applications for the tender is 9 May.

Ostwind 3 is the third offshore project for the grid connection of the wind farm areas to the northeast of Rügen island, following Ostwind 1 and Ostwind 2.

The wind farm area connecting to Ostwind 3, designated as O-1.3, is located in the area Westlich Adlergrund, north of the operating wind farms Wikinger and Arkona from 50Hertz’s operational grid connection project Ostwind 1.

Recently, the German TSO contracted Heinrich Hirdes EOD Services for UXO identification and removal works at the project.

The objective of the campaign is to mitigate the risk of UXO present in the cable installation corridors to ensure a safe installation of the Ostwind 3 export cables and offshore substation, including all route clearance and route preparation activities.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

GridOffshore WindSubseaSurveys & InterventionsBusiness & FinanceBusiness Developments & ProjectsOperations & MaintenanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free