Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Shell’s subsea compression project off Norway to assist in keeping up gas supply to Europe
Fossil Energy

July 11, 2022 · about 4 years ago

Shell’s subsea compression project off Norway to assist in keeping up gas supply to Europe

Shell has received approval from Norway’s authorities for a development plan for its gas subsea compression project in the Norwegian Sea.

3 minutes read
  • LinkedIn
  • X
  • Email
Shell’s subsea compression project off Norway to assist in keeping up gas supply to Europe
Ormen Lange development; Source: Shell

UK-headquartered energy giant Shell has received approval from the Norwegian authorities for a development plan related to its gas subsea compression project in the Norwegian Sea, which is expected to lead to increased gas extraction from this field.

Back in September 2021, Shell submitted its plan for development and operation (PDO) for the Ormen Lange wet gas subsea compression project to the Ministry of Petroleum and Energy. As reported at the time, the project was expected to unlock an additional 30-50 billion cubic meters of natural gas , leading to an increase in Ormen Lange’s overall gas recovery rate.

Related Articles

Authorities & Government

Shell sanctions Norwegian subsea compression project

2 min read

In an update on Friday, the Norwegian Ministry of Petroleum and Energy informed that it had approved the plan for the further development of the Ormen Lange field.

Terje Aasland , Norway’s Minister of Petroleum and Energy, remarked: “This project will increase recovery from the Ormen Lange field from 75 to 85 per cent, at the same time as gas production from the field is accelerated. This project helps to maintain the gas supply from Norway to our friends in Europe from the middle of this decade.”

Moreover, the goal of the project is to increase gas extraction from Ormen Lange by up to 40 billion standard cubic meters (Sm 3 ) of gas and the expected start-up of the project is anticipated in 2025. The project entails the installation of a wet gas compressor system on the seabed at a 900-metre depth close to the wellheads, increasing gas flow from the reservoir into the wells.

The investments in this project amount to approximately NOK 11.7 billion (around $1.2 billion), and the project is expected to contribute to the development of key expertise and new technology within seabed compression and transmission of power over long distances underwater, with Norwegian supplier companies at the forefront, says the Norwegian Ministry of Petroleum and Energy.

“This project is another proof of how far you get with high competence and innovation. The innovative seabed compression that will now be used is a first-class technology project that there is reason to be proud of,” concluded Aasland.

The subsea systems for Shell’s Ormen Lange project will be manufactured and installed by OneSubsea and Hitachi Energy has started testing what is said to be the world’s most powerful 24-MVA subsea transformer, which will be supplied to OneSubsea to power the compression system for this field.

Related Articles

Fossil Energy

Hitachi testing ‘world’s most powerful’ subsea transformer for Ormen Lange compression system

2 min read

Located 120 kilometres (75 miles) off the coast of Norway, the deep-water Ormen Lange field produces gas, which meets around 20 per cent of the UK’s gas needs. It was discovered in 1997 while the original plan for development and operation was approved in 2004. The field was put into production in 2007.

The Ormen Lange field operates without a platform and includes 19 wells divided between four templates on the seafloor while two 30-inch pipelines transport the gas to the Nyhamna terminal for processing, where it is separated into natural gas and condensate for export prior to being exported via Sleipner to Easington.

Shell is the operator of the project with 17.81 per cent interest while its partners are Petoro (36.48 per cent), Equinor (25.34 per cent), PGNiG Upstream Norway (14.02 per cent) and Vår Energi (6.33 per cent).

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyOil & GasSubseaAuthorities & GovernmentBusiness & FinanceBusiness Developments & ProjectsExploration & ProductionProject & TendersRegulation & PolicyRules & Regulation

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Saipem hands Saudi jack-up fleet to ADES in strategic shallow-water exit
  2. 2Valeura advances Gulf of Thailand expansion with PTTEP farm-in approval
  3. 3Santos broadens Asia-Pacific LNG portfolio with Canadian supply and 10-year POSCO deal
  4. 4Borr Drilling keeps three jack-up rigs as it reorganizes Mexico ops with stake sale

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free