U.S.-based contractor McDermott International has completed the load out of the Tyra East G (TEG) gas processing module for the TotalEnergies-operated Tyra field for next week’s sail away towards the Danish North Sea.
As reported in early August, TotalEnergies revised the first gas date for the Tyra redevelopment project amid global supply chain challenges that impacted the extent to which fabrication work on the process module (the TEG) was being completed in the yard in Batam, Indonesia.