Home›Cabling›Jan De Nul consortium bags BalWin4 and LanWin1 cable contracts
Cabling

December 6, 2023 · about 2 years ago

Jan De Nul consortium bags BalWin4 and LanWin1 cable contracts

Jan De Nul Group, together with its consortium partners LS Cable & System and Denys, has signed contracts for two 525 HVDC cable systems serving the two grid connection systems for BalWin4 and LanWin1. These mark the first two contracts signed under the long-term framework agreement that TenneT and

2 minutes read
  • LinkedIn
  • X
  • Email
Jan De Nul BalWin4 LanWin1
Fleeming Jenking, Jan De Nul’s ULEv XL cable-laying vessel.

Jan De Nul Group, together with its consortium partners LS Cable & System and Denys, has signed contracts for two 525 HVDC cable systems serving the two grid connection systems for BalWin4 and LanWin1.

These mark the first two contracts signed under the long-term framework agreement that TenneT and Jan De Nul inked earlier this year.

The projects comprise the design, manufacturing, transport, installation, protection, and testing of three 525 kV cable systems for connecting offshore wind farms to the onshore grid via the BalWin4 and LanWin1 grid connections.

Jan De Nul will take care of the transport, installation, burial, and protection of the offshore cables. For this, the company will use a variety of its specialized vessels and assets including the Fleeming Jenkin, the firm’s recently ordered XL cable-laying vessel.

Related Articles

Cabling

Jan De Nul orders world’s largest cable-laying vessel from China

2 min read

LS Cable & System will design, manufacture, terminate, and test all cables with Denys being responsible for civil and cable pulling scope related to the onshore cable routes.

In total, more than 1,000 kilometers of HVDC will be designed, manufactured, transported, installed, protected, and tested for these two projects.

“We are delighted to sign these first two projects under the partnership frame agreement we signed earlier this year with TenneT. This marks an important milestone in support of TenneT’s 2GWProgram and the construction of the energy transition,” said Wouter Vermeersch , Manager of Offshore Cables at Jan De Nul Group.

The cable systems of the two grid connections BalWin4 and LanWin1 coming from the offshore converter stations will cross the Wadden Sea and be connected to the extra-high voltage grid in Unterweser.

The grid connections will enable renewable electricity from offshore wind farms with a total transmission capacity of 4 GW to be fed into the German grid.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingDeepwater InstallationGridOffshore WindSubseaVessels & VehiclesBusiness Developments & ProjectsEquipmentOperations & MaintenanceProject & TendersVessels

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Hybrid electric propulsion at the heart of next-gen LNG carrier design
  2. 2Shell and MET Group pen new multi-year US LNG supply deal
  3. 3New US wave power test facility on Carnegie Clean Energy contender list for potential CETO demo
  4. 4Germany-UAE energy ties deepen as RWE, Masdar and ADNOC eye LNG supply and €3B offshore wind investment

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free