The IAC termination and testing works, which are currently underway and are being performed by the Normand Navigator vessel, are expected to continue until May 2024.
The 450 MW Neart na Gaoithe offshore wind farm, located some 15 kilometers off the coast of Fife in Scotland, is expected to produce its first power this year.
The first of its 54 Siemens Gamesa 8 MW wind turbines was installed in July 2023 .
Neart na Gaoithe is owned by the joint venture between EDF Renewables and ESB.