Offshore Energy
  • news
  • test
JobsNewsletter
Offshore Energy logo

© 2026 Navingo. All rights reserved.

Home›Business Developments & Projects›300 MW offshore wind farm expansion project in Zhanjiang enters operation
Business Developments & Projects

December 26, 2024 · about 1 year ago

300 MW offshore wind farm expansion project in Zhanjiang enters operation

A 300 MW expansion to the existing 600 MW Xuwen offshore wind farm in Zhanjiang, China, developed by State Power Investment Corporation (SPIC), has started commercial operation. The 600 MW Xuwen offshore wind farm was built in two phases consisting of a total of 94 wind turbines. The first of 47 Min

2 minutes read
  • LinkedIn
  • X
  • Email
Dorian LPG takes over newbuild dual-fuel LPG and ammonia gas carrier

Share this article

A 300 MW expansion to the existing 600 MW Xuwen offshore wind farm in Zhanjiang, China, developed by State Power Investment Corporation (SPIC), has started commercial operation.

The 600 MW Xuwen offshore wind farm was built in two phases consisting of a total of 94 wind turbines. The first of 47 Mingyang’s MySE6.45-180 turbines in the first phase was installed in early 2021 and the entire wind farm was commissioned at the end of 2021 .

The work on the additional 300 MW started in 2023 with wind turbine installation commencing in the spring of 2024. According to a social media post shared by SPIC, the expansion went into operation on December 17.

This content is available after accepting the cookies.

A major milestone for offshore #WindEnergy in #Guangdong has just been achieved! On December 17, the Xu Wen Offshore Wind Power Expansion Project in #Zhanjiang became the province's first fully connected offshore wind power project in 2024. With a total installed capacity of 300… pic.twitter.com/W0AvpPib6x

The news about the start of the wind farm’s commercial operation was also shared by Hengtong Submarine Power Cable, which was engaged in the project under an EPCI contract.

Hengtong was responsible for the high voltage inter-array and export cable system, as well as the installation of foundations and the offshore substation. To carry out the work, Hengtong used its cable laying vessel Hengtong Cable 5 and crane vessel Hengtong 3500 , the company said in a social media post on December 26 .

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Business Developments & Projects

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1ADES jack-up rig pair lines up drilling jobs in Nigerian and UK waters
  2. 2Odfjell Drilling’s rig remaining with Norwegian oil & gas operator for another year
  3. 3Karoon boosts Brazilian field’s oil output with all wells now online
  4. 4TotalEnergies offloading Mexican shallow water block to Grupo Carso

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free