Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo
Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›All inter-array cables in place at French 488 MW offshore wind farm
Cabling

June 24, 2025 · about 1 year ago

All inter-array cables in place at French 488 MW offshore wind farm

The final inter-array cable was installed at the 488 MW Îles d’Yeu and Noirmoutier (EMYN) offshore wind farm in France, developed by Les Éoliennes en Mer Services. The 61st and final inter-array cable was installed at the EMYN site located 11.7 kilometers from the island of Yeu and 16.5 kilometers f

1 minutes read
  • LinkedIn
  • X
  • Email
Dorian LPG takes over newbuild dual-fuel LPG and ammonia gas carrier
PPF; Source: ConocoPhillips

The final inter-array cable was installed at the 488 MW Îles d’Yeu and Noirmoutier (EMYN) offshore wind farm in France, developed by Les Éoliennes en Mer Services.

The 61st and final inter-array cable was installed at the EMYN site located 11.7 kilometers from the island of Yeu and 16.5 kilometers from the island of Noirmoutier.

According to a recent social media post by Louis Dreyfus TravOcean, this accomplishment paves the way for a transmission capacity of 512 MW.

Geoquip Marine’s Geoquip Elena will be demobilised early July from the company’s Dunkirk offshore base.

In addition, the termination and testing activities carried out by Prysmian from the service operation vessel (SOV) Island Diligence, owned by Island Offshore, are on track to be completed in July, said Louis Dreyfus TravOcean.

Related Articles

Cabling

Installation of final inter-array cables about to start at Îles d’Yeu and Noirmoutier project site

2 min read

The monopile installation work was completed at the EMYN site this month by DEME Group’s Innovation jack-up vessel.

The first of 61 Siemens Gamesa 8 MW turbines was installed on its foundation in May 2025. The remaining 60 turbines are scheduled to be installed between May and September 2025 by Jan De Nul’s Vole au Vent.

At the beginning of this month, the 488 MW offshore wind farm started supplying green electricity to the French grid, following a successful initial testing phase that began on May 23.

Îles d’Yeu and Noirmoutier project is scheduled to be fully commissioned by the end of 2025.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingDeepwater InstallationOffshore WindSubseaWind FarmsBusiness Developments & ProjectsOperations & MaintenanceProject & Tenders

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norwegian PSV to continue current charter for additional 100 days
  2. 2Italy’s NextGeo to open office in Germany
  3. 3TotalEnergies finds more oil off Angola, enters two exploration blocks
  4. 4Odfjell Drilling’s new rig busy until 2031 thanks to deal with Vår Energi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free