Home›Cabling›Surveys to begin at Ireland-Wales interconnector in ten days
Cabling

July 8, 2025 · about 1 year ago

Surveys to begin at Ireland-Wales interconnector in ten days

Belgian GeoXYZ will be kicking off site investigations this month for a 750 MW electricity interconnector that will link Ireland and Wales. The MaresConnect interconnector will comprise a cable route of approximately 245 kilometers under the sea and underground between Dublin in Ireland and Bodelwyd

2 minutes read
  • LinkedIn
  • X
  • Email
Surveys to begin at Ireland-Wales interconnector in ten days
Geo Ocean VI. Source: GeoXYZ

Belgian GeoXYZ will be kicking off site investigations this month for a 750 MW electricity interconnector that will link Ireland and Wales.

The MaresConnect interconnector will comprise a cable route of approximately 245 kilometers under the sea and underground between Dublin in Ireland and Bodelwyddan, Denbighshire in Wales.

The 750 MW electricity link is being developed by MaresConnect Limited, owned by Foresight Group’s energy transition fund, Foresight Energy Infrastructure Partners (FEIP) , and Etchea Energy Nominees Limited (EENL).

GeoXYZ will deploy the 53.8-meter-long Geo Ocean VI to complete geophysical survey operations. The vessel will survey a 500-meter corridor along the planned route in Irish waters, using multibeam echosounder, side-scan sonar, magnetometer and sub-bottom profilers.

Furthermore, the vessel will complete environmental sampling operations along the proposed subsea cable route, as well as geotechnical sampling operations, with locations to be determined following the geophysical survey.

The survey operations are planned to start on July 18, weather permitting. The expected duration for all works is up to 44 days, including weather and other downtime, with completion expected by August 31.

MaresConnect is an integral part of the MARES project, which aims to integrate 1,750 MW of new renewable energy sources and 6 GWh of pumped hydro energy storage (PHES) in Mayo in the west of Ireland to the GB and SEM networks, as well as provide increased interconnector capacity and voltage stability.

The project secured an interconnector license from Ofgem in June 2022 and a 750 MW grid connection agreement at the National Grid’s Bodelwyddan substation. At the end of 2024, Great Britain’s energy market regulator approved the interconnector .

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingInterconnectorsSubseaSurveys & InterventionsBusiness & FinanceBusiness Developments & ProjectsOutlook & StrategyProject & TendersTransitionVision

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norwegian PSV to continue current charter for additional 100 days
  2. 2Italy’s NextGeo to open office in Germany
  3. 3TotalEnergies finds more oil off Angola, enters two exploration blocks
  4. 4Odfjell Drilling’s new rig busy until 2031 thanks to deal with Vår Energi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free