Home›Fossil Energy›Brazilian FPSO weeks away from restart following oil production shutdown
Fossil Energy

August 18, 2025 · about 1 year ago

Brazilian FPSO weeks away from restart following oil production shutdown

Norway’s state-owned energy giant Equinor has switched off oil production at its largest operated field outside the European country.

2 minutes read
  • LinkedIn
  • X
  • Email
FPSO Peregrino; Credit: Felipe Torres/Equinor
FPSO Peregrino; Credit: Felipe Torres/Equinor

Norway’s state-owned energy giant Equinor has switched off oil production at its largest operated field outside the European country. This field is located off the coast of Brazil.

The production halt followed the decision the National Agency of Petroleum, Natural Gas and Biofuels (ANP) made to stop production on the FPSO Peregrino , operated by Equinor do Brasil, as communicated to the consortium partners of the asset through the Operational Safety Superintendence.

According to PRIO, which set the wheels in motion to acquire Equinor’s interest in the field a few months ago, the main areas for improvement identified in the notice issued by ANP are risk management and assessment documentation, and adjustments to the deluge system. The FPSO Peregrino, which has an oil processing capacity of 110 kbbl/d and 300 kbbl/d of water, operates at the field.

Related Articles

Fossil Energy

Equinor bids adieu to its largest offshore asset outside Norway for $3.5 billion

4 min read

Equinor, said to have immediately initiated the required adjustments as the operator of the asset, aims to meet the requirements as swiftly and accurately as possible, estimating that the works will take between three and six weeks to be fully completed.

PRIO claims to be working with Equinor to contribute all possible resources towards the resolution of these matters, not only in its role as a consortium partner but also as the future operator of the asset.

The Peregrino field, discovered in 1994, had its first oil in 2011. Located 85 kilometers off the coast in the Campos Basin, the asset lies within blocks BM-C-7 and BM-C-47, and 28 kilometers from the Polvo and Tubarão Martelo cluster.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyOil & GasBusiness & FinanceBusiness Developments & ProjectsExploration & Production

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1SED Energy Holdings and Ventura Offshore to unite into one
  2. 2New Boskalis rock installation vessel starts work offshore Poland
  3. 321 companies apply for Norway’s new oil & gas exploration areas
  4. 4Spanish shipyard launches its largest-ever vessel, built for Østensjø Rederi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free