The Site Acceptance Tests (SAT) for the Hollandse Kust West Beta cables have been completed in the Dutch North Sea. The substation will connect the OranjeWind offshore wind farm, developed by RWE and TotalEnergies, to the onshore electricity grid.
The testing of two 220 kV export cable systems for power transmission to shore, as well as one 66 kV interconnector cable between Hollandse Kust West Alpha and Hollandse Kust West Beta, was completed in one week. The two substations will connect the wind farms from the Hollandse Kust West area in the North Sea to the grid on land.