Home›Cabling›OWC wins cable engineering contract for Scottish floating wind farm
Cabling

August 29, 2025 · about 1 year ago

OWC wins cable engineering contract for Scottish floating wind farm

The renewable energy consultancy OWC has been awarded a contract to provide cable engineering support to the Green Volt floating offshore wind farm in Scotland, developed by Flotation Energy and Vårgrønn. OWC’s scope of work includes cable engineering for both offshore and onshore cables. The subsea

2 minutes read
  • LinkedIn
  • X
  • Email
Green Volt Rovco
Source: Green Volt Floating Offshore WindFarm

The renewable energy consultancy OWC has been awarded a contract to provide cable engineering support to the Green Volt floating offshore wind farm in Scotland, developed by Flotation Energy and Vårgrønn.

OWC’s scope of work includes cable engineering for both offshore and onshore cables. The subsea scope focuses primarily on the export cable, but OWC will also support inter-array cable system design and alignment.

The onshore engineering scope includes technical responsibility for the cable that runs from the landfall site near Aberdeen to an onshore substation.

The company’s operation in Scotland will manage the cable engineering work scope, which is planned to be completed later this year.

The cable engineering package is the latest of many OWC assignments at the Green Volt project, which the company has supported since May 2023, including the provision of a range of owner’s engineering services.

OWC’s involvement so far spans over 15 project roles, including wind turbine package manager, certification manager, metocean lead, and project risk lead, as well as technical scopes such as Contracts for Difference (CfD) requirements studies, concept engineering reviews, and port and cable assessments.

“We are proud to be part of such a pioneering project and to contribute with Scotland-based expertise to solve another key part of the project. Green Volt both advances floating wind and redefines how offshore energy systems can be decarbonised,” says Johnathan Love , OWC Project Manager for Green Volt.

The Green Volt floating offshore wind farm is one of the Scottish INTOG round winners and projects planned to provide electricity to oil and gas platforms.

The developers recently awarded a Front-End Engineering and Design (FEED) contract to Worley for the onshore substation.

The project is planned to have up to 35 floating wind turbines, totalling up to 560 MW in installed capacity.

Last year, Green Volt secured both onshore and offshore planning consents and a Contract for Difference (CfD) in the UK’s Allocation Round 6 (AR6) as the only floating wind project awarded the contract in the round.

Related Articles

Offshore Wind

TGS performing geophysical survey for floating wind farm planned to power oil & gas platforms

2 min read

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingOffshore WindSubseaSurveys & InterventionsWind FarmsBusiness & FinanceBusiness Developments & ProjectsOperations & Maintenance

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norwegian PSV to continue current charter for additional 100 days
  2. 2Italy’s NextGeo to open office in Germany
  3. 3TotalEnergies finds more oil off Angola, enters two exploration blocks
  4. 4Odfjell Drilling’s new rig busy until 2031 thanks to deal with Vår Energi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free