Offshore construction at the project site(s), located some 37 and 22 kilometers from the coastline near Ustka and Łeba, began earlier this year. The 2026 construction campaign will include the installation of 100 monopiles, transition pieces (TPs), offshore substation components, subsea cables and supporting infrastructure.
Related Article
Offshore construction on Polish Bałtyk 2 & 3 wind farms starts with subsea rock installation
The installation of wind turbines is scheduled to begin in 2027, along with the outfitting of the offshore substations. The first electricity from the offshore wind farms is expected in 2027, with full commercial power production scheduled in 2028.