Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›Australia: Heron South-1 Production Testing Preparations Taking Longer Than Expected
Subsea

November 7, 2012 · about 14 years ago

Australia: Heron South-1 Production Testing Preparations Taking Longer Than Expected

MEO Australia Limited provides the following update in relation to Heron South-1 being drilled in NT/P68, operated by Eni Australia Ltd (Eni). Since last progress report the 178mm (7”) liner was run to 4,255mMDRT. The forward plan is to complete cementing the 7” liner in place with the intention to

1 minutes read
  • LinkedIn
  • X
  • Email

MEO Australia Limited provides the following update in relation to Heron South-1 being drilled in NT/P68, operated by Eni Australia Ltd (Eni).

Since last progress report the 178mm (7”) liner was run to 4,255mMDRT.

The forward plan is to complete cementing the 7” liner in place with the intention to install a 114mm (4½”) slotted liner to 4,454mMDRT prior to conducting separate production tests over two intervals.

The well is interpreted to have intersected two gross sandstone intervals of approximately 120m and 115m thickness separated by approximately 130m of shale and silt. Eni has advised that it intends to carry out two separate production tests to determine reservoir productivity and gas composition of each interval.

In accordance with pre drilling plans, the well will be plugged and abandoned at the conclusion of production testing.

MEO’s CEO and MD Jürgen Hendrich commented on the announcement:

“Eni is working diligently towards production testing the two zones of interest. Preparations to allow production testing are obviously taking a little longer than anticipated. The 7” liner did not reach total depth, hence the intention to run a 4½” slotted liner to allow access to the lower zone.”

[mappress] Press Release, November 07, 2012

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaBusiness & FinanceOperations & Maintenance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free