Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Norway’s Sevan Drilling Provides Rig Fleet Status Update
Fossil Energy

January 3, 2013 · about 13 years ago

Norway’s Sevan Drilling Provides Rig Fleet Status Update

Norwegian drilling contractor, Sevan Drilling, today announced its fleet status update for December 2012. Sevan Driller rig achieved a technical uptime of 92.7% in December 2012. On 29 December Sevan Driller successfully completed the well it was drilling in the Santos basin and moved to Guanabara B

2 minutes read
  • LinkedIn
  • X
  • Email

Norwegian drilling contractor, Sevan Drilling, today announced its fleet status update for December 2012.

Sevan Driller rig achieved a technical uptime of 92.7% in December 2012. On 29 December Sevan Driller successfully completed the well it was drilling in the Santos basin and moved to Guanabara Bay offshore Rio de Janeiro.

As previously announced, Sevan Drilling will perform required maintenance on the dynamic positioning and electrical systems on the rig and in addition, they will complete the three-year compulsory marine hull survey. The maintenance and the marine hull survey are in total estimated to last for 20 days and Sevan Drilling will receive 90% of the contract day rate during this period.

Sevan Brasil

Sevan Brasil rig achieved a technical uptime of 97.0% in December 2012.

Sevan Drilling Rig no 3

Construction of Sevan Drilling Rig no 3 is progressing according to plan and reached 64.5% overall completion in December 2012. The drill-floor, derrick and living quarters were lifted and integrated to the main hull in November 2012. Preparation for commissioning has started and commissioning of the first systems will begin in Q1 2013.

Sevan Drilling Rig no 4

Construction of Sevan Drilling Rig no 4 is also progressing according to plan and reached 51.8% overall completion in December 2012. The main deck is now lifted and integrated to the hull. Lifting of modules up to upper deck will start according to plan January 2013. The drill floor, living quarters and derrick will be lifted and integrated to the main hull in Q1 2013.

[mappress]

January 3, 2013

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free