Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Denmark to Launch Offshore Wind Tenders, Timetable Now Ready
Wind Farms

January 31, 2013 · about 13 years ago

Denmark to Launch Offshore Wind Tenders, Timetable Now Ready

The Danish Energy Agency (DEA) has published details of the tender process and the provisional timetable for the planned 1,500 MW of offshore wind power to be set up by 2020. Since March 2012, it has been evident that Denmark should have two large offshore wind farms and several coastal offshore win

2 minutes read
  • LinkedIn
  • X
  • Email

The Danish Energy Agency (DEA) has published details of the tender process and the provisional timetable for the planned 1,500 MW of offshore wind power to be set up by 2020.

Since March 2012, it has been evident that Denmark should have two large offshore wind farms and several coastal offshore wind turbines to meet the goal of 50% of wind energy in the electricity mix by 2020.

The tender process kicks off in 2013

DEA will initiate the tender process for the two large offshore wind farms in 2013; however, the process for Horns Rev 3 is expected to be settled at the beginning of 2015, while the outcome of the tender for Krieger’s Flak must wait until the end of the same year.

Results of the geophysical surveys for Horns Rev 3 and Krieger’s Flak are expected to be published no later than March 31, 2013. The preliminary results of the studies will be presented already in February, during a seminar at the EWEA Exhibition in Vienna, Austria.

The prior information notice on the award of Horns Rev 3 and Krieger’s Flak will be published during 2013, with which the formal tender process kicks off.

Timetable for offshore wind turbines is established

After a political agreement reached in March 2012, six areas have been identified for the offshore wind turbines at: Bornholm, Smålandsfarvandet, Sejero Bay, Sæby, and the southern and northern areas of the Danish North Sea. Feasibility studies for those areas have been initiated in January 2013 and prior notice of availability will be published during 2013.

Besides these areas, the candidates for installation of offshore wind turbines are also Mejl Flak and Nissum Bay. If applicants would decide to be part of the tender process and there is support among the relevant local authorities, the number of coastal areas that are offered increases to eight. A draft of EIA (Environmental Impact Assessment) for Mejl Flak and Nissum Bay has already been published.

The results of the geophysical survey for the coastal wind turbines are expected to be published until November 3rd, 2014. In addition, a comprehensive draft of EIA will be available for public consultation no later than February 16 th 2015.

DEA has scheduled the deadline for submission of bids to be in autumn2015, and concessions and construction permits are also expected to be issued before the end of 2015.

[mappress]

Offshore WIND Staff, January 31, 2013; Image: energinet.dk

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsAuthorities & GovernmentProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Expro lines up 14-well Canadian offshore life-extension campaign
  2. 2TotalEnergies greenlights gas project to feed one-third of Nigeria LNG train expansion
  3. 3Construction ramps up at Orkney Islands’ first link to UK mainland
  4. 4Perenco on offshore platform electrification quest to power Brazil’s shallow-water fields from shore

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free