Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Fifth Season of Fox River Dredging Ends (USA)
Dredging

November 18, 2013 · about 13 years ago

Fifth Season of Fox River Dredging Ends (USA)

The fifth season of PCB cleanup from the Fox River comes to an end. This work included dredging in a number of areas between the De Pere dam and the project’s processing facility in Green Bay. Progress for the week ending November 9: – Estimated volume of sediment dredged – 12,744 cubic yards; – Est

1 minutes read
  • LinkedIn
  • X
  • Email

The fifth season of PCB cleanup from the Fox River comes to an end.

This work included dredging in a number of areas between the De Pere dam and the project’s processing facility in Green Bay.

Progress for the week ending November 9:

– Estimated volume of sediment dredged – 12,744 cubic yards;

– Estimated amount of processed sediment produced – 6,515 tons;

– Estimated tonnage hauled to the landfill – 3,808 tons;

– Truckloads to the landfill – 159;

– Water treated and discharged to the river – 25,500,000 gallons;

– Area of river bottom sand covered – 5.29 acres;

– Area of gravel cover – 0 acres.

Progress during the 2013 dredging, capping and covering season (through November 9):

– Estimated volume of sediment dredged – 570,902 cubic yards;

– Estimated tonnage of sediment produced – 256,418 tons;

– Estimated tonnage hauled to the landfill – 276,982 tons;

– Truckloads to the landfill – 11,586;

– Water treated and discharged to the river – 853,500,000 gallons;

– Area of river bottom sand covered – 106.62 acres;

– Area of gravel cover – 13.41 acres.

The project officially started with dredging and processing on April 28, 2009.

More info

[mappress]

Press Release, November 18, 2013

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceEquipmentTechnology

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free