Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Shipbuilding›FS ‘Stormy’ Ready for Outfitting in Leirvik (Norway)
Shipbuilding

November 22, 2013 · about 13 years ago

FS ‘Stormy’ Ready for Outfitting in Leirvik (Norway)

The hull of Havyard Ship Technology’s newbuild number 117, a Havyard 587 wellboat for the shipping company Fosnavaag Shipping, has arrived at the shipyard in Leirvik and is facing a hectic period of outfitting and testing. In August 2012, Havyard agreed a contract with Fosnavaag Shipping for the con

3 minutes read
  • LinkedIn
  • X
  • Email

The hull of Havyard Ship Technology’s newbuild number 117, a Havyard 587 wellboat for the shipping company Fosnavaag Shipping, has arrived at the shipyard in Leirvik and is facing a hectic period of outfitting and testing.

In August 2012, Havyard agreed a contract with Fosnavaag Shipping for the construction of the world`s most efficient and environmentally friendly wellboat. The Havyard 587 design was developed in close cooperation with ship owner and key suppliers of vital systems onboard.

The hull of the ship has been constructed at the Cemre shipyard in Turkey, where Havyard constructs most hulls for their newbuilds. The hull arrived last week at Havyard`s own shipyard in Leirvik in Sogn, Norway, where completion of the outfitting and testing will take place.

Jobjørn Løland, Project Manager for newbuild 117 at the Leirvik shipyard said that there was close cooperation with the site-team in and that there were quite a few trips to Turkey in the early project phase.

“ It is important to follow up on the progress there. In the project organization we have experts in every special field, and as the hull nears completion, the production organization in Leirvik becomes more and more involved, ” he continued.

The newbuild went straight into dock as it arrived at the shipyard and according to plan it will remain there until the end of February. Also the main engines will be started up while in dock.

“The largest pipes have been assembled in Turkey but all installations of machines and engines, outfitting and accommodation will be performed in Leirvik, in addition to painting and start-up ,” Løland pointed out.

Yard Director Trygve Solaas pointed out that proximity to customers is also an advantage:

“ Demanding customers who know what they want and who challenge us are very important. It is the best way to improve. In Norway we cannot be the cheapest, but we deliver a first-class product. Our most important motivation is that the customer is satisfied and feels that he gets at least what he pays for.

“In this project there have been quite a few technical innovations developed in close cooperation with shipping company and equipment supplier. This forces us to think outside the box and we get to put new ideas into effect. That’s exciting” , concludes Trygve Solaas.

Efficient and environmentally friendly fish transport

Havyard 587 contains the best within wellboat technology, setting a new standard for environmentally friendly and gentle transport and treatment of live fish.

“Cylindrical cargo tanks and the efficient filter- and water treatment equipment make it possible to perform a closed transport across far longer distances compared to existing boats,” says Olav Remøy, CEO of Fosnavaag Shipping . ” This makes greater density of fish possible with a more gentle treatment of the live fish leading to better quality of the end product. There has also been put great emphasis on the hull and propulsion machinery to be as efficient as possible in real operating conditions, so that fuel economy is the best possible and that emissions are as low as possible.”

Delivery of newbuild 117 is set for March 2014.

[mappress]

Havyard, November 22, 2013

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

ShipbuildingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1QatarEnergy’s CEO: Repairs on damaged LNG trains to take three years
  2. 2Remote operations center for unmanned survey operations opens in Singapore
  3. 3Australian oil & gas firm makes its first foray into Liberia’s deepwater arena
  4. 4Brazilian subsea services provider changes hands

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free