Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›KS Drilling stalls jack-up delivery from COSCO
Fossil Energy

July 13, 2015 · about 11 years ago

KS Drilling stalls jack-up delivery from COSCO

KS Drilling, an international drilling company that is part of the KS Energy Group, and COSCO Nantong have mutually agreed to extend, by way of an amendment agreement, the delivery date for a rig that COSCO is building until April 30, 2016. The rig was originally scheduled for delivery in first quar

2 minutes read
  • LinkedIn
  • X
  • Email

KS Drilling, an international drilling company that is part of the KS Energy Group, and COSCO Nantong have mutually agreed to extend, by way of an amendment agreement, the delivery date for a rig that COSCO is building until April 30, 2016.

The rig was originally scheduled for delivery in first quarter 2014.

To remind, the two companies entered the shipbuilding contract for two drilling rigs based on the LeTourneau Technologies, Inc. WORKHORSE Class design in May 2011. The first rig had been delivered in 2014 while the second jack-up is ready to be delivered.

Under the amendment agreement, the KS Drilling is entitled to take delivery of the rig at any time prior to April 30, 2016. Payment of the rig will be made within 5 working days after the rig has been accepted.

Furthermore, COSCO Nantong and KS Drilling have also agreed that either party will be entitled to sell the rig to a third party if the offer could recover their respective costs, or the parties could negotiate in good faith for a compromised solution to sell the rig.

In the event that prior to April 30, 2016, KS Drilling does not take delivery of the rig or if the rig is not sold; and KS Drillng fails to place a new order for one LeTOURNEAU WORKHORSE or one Super 116E design jack-up drilling rig with COSCO Nantong, KS Drilling will pay interest on any remaining payment on the rig at the rate of three month London Interbank Offered Rate plus 1.5% per annum, calculated from May 1, 2015 to the date of payment to COSCO Nantong.

COSCO said it is not able to ascertain the financial impact of the amendments at this point in time as there is no certainty as to the eventual outcome of the options under the amendment agreement.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyBusiness & FinanceExploration & Production

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Expro lines up 14-well Canadian offshore life-extension campaign
  2. 2TotalEnergies greenlights gas project to feed one-third of Nigeria LNG train expansion
  3. 3Construction ramps up at Orkney Islands’ first link to UK mainland
  4. 4Perenco on offshore platform electrification quest to power Brazil’s shallow-water fields from shore

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free