Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Laying of Block Island Mainland Link to Start This Week
Wind Farms

June 1, 2016 · about 10 years ago

Laying of Block Island Mainland Link to Start This Week

The Big Max cable laying barge will start installing the 20-mile submarine cable which will export the electricity produced by the the first US offshore wind farm, the 30MW Block Island, to the mainland later this week. The National Grid (Sea2Shore) subsea cable will connect Block Island, to Naragan

2 minutes read
  • LinkedIn
  • X
  • Email

The Big Max cable laying barge will start installing the 20-mile submarine cable which will export the electricity produced by the the first US offshore wind farm, the 30MW Block Island, to the mainland later this week.

The National Grid (Sea2Shore) subsea cable will connect Block Island, to Naragansett, Rhode Island.

The installation works will begin at Scarborough Beach, where the Big Max and associated support vessels will be positioned off the shore of Scarborough Beach for a couple of days while the submarine cable is fed through the conduit and into the land/sea transition vault.

Once the cable is secured in the vault, the barge will begin the approximate two week, 20-mile journey to Block Island, burying the cable roughly 4-6 feet below the sea floor.

The Horizontal Directional Drilling (HDD) operation was completed at Scarborough Beach ahead of the installation works, and all associated equipment is in the process of demobilization.

Crews also completed the installation of the land/sea transition vault where the submarine and land cables will connect in the Scarborough Beach parking lot. Restoration and other connection efforts will continue in the vicinity.

All of the manholes and duct bank, with the exception of the duct bank immediately in front of the Wakefield substation, have been installed and crews will be pulling wire underground along the route for the next few weeks, with the work expected to conclude for the season on 24 June.

The Big Max started laying the 8-mile subsea link between the wind farm and the substation on Block Island in early May. The works were completed on 27 May.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free